Eichholtz Suite 160 TI — Construction Cost Tracker

Tivoli Village, Las Vegas | Updated June 28, 2026 — Pay App 3 (Inv #1272, $144,835.50) received; 6-month promissory note for $220,813.50 balance; full LV Builders contract now billed

Base Contract
$347,055
AIA A101, Sep 18 2025
Change Orders
$27,875
2 change orders, 0 duplicates flagged
Current Total
$390,767
Jones Sign $12,275 net + Precision Tint $3,562 (paid full)
Paid to Vendors (QBO)
$170,920
$154,117 LV Builders + $13,241 Jones Sign + $3,562 Precision Tint · 44% of $390,767 project
Balance Due
$220,814
$75,978 Pay App #2 + $144,836 Pay App #3 · promissory note issued · $90K due 7/1/2026 · Jones Sign + Precision Tint settled
Turnover Target
May 22, 2026
Per LV Builders schedule (4/8/26)
Project Updates
Cost Composition
$390,767 Total Project Cost
$347,055
Base Contract
88.8%
$19,285
CO-1 Cabinetry
4.9%
$8,590
CO-2 Air Curtain / Outlets
2.2%
$12,275
Jones Sign Co
3.1%
$3,562
Precision Tint
0.9%
Original Bid by CSI Division
Finishes
100%
Mechanical
79.5%
Electrical
51.5%
Metals
25.8%
Gen Conditions
18.9%
Sitework/Demo
18.9%
Doors & Windows
18.6%
Fire Alarm
11.2%
Concrete
3.7%
Specialties
3%
Change Order Log
CO #DateDescriptionCSI DivisionSubtotalOH + Fee (15%)TotalStatusDuplicate?
CO-13/5/2026 28 LF laminated cabinets + SS countertops (28 ft + 13 ft bar top) 06 — Wood & Plastics$16,697$2,588$19,285 Approved ✓ New Scope ✓
CO-23/24/2026 Air curtain at main entry (code-required) + 12 new circuits for break area & owner-requested outlets 15/16 — Mech + Elec$7,437$1,153$8,590 Approved ✓ New Scope ✓
⚠ Note: Base electrical ($32,400) covers outlets per code. The 12 extra circuits are owner additions. Air curtain is new code requirement. Verify break area circuits were not in original electrical plan.
$24,134$3,741$27,875
Vendor Cost Breakdown
VendorRoleAmount% of TotalStatus
LV Builders LLCGeneral Contractor$374,93095.9% Pay App #1 PAID ($104,117 ✓); Pay App #2 ($125,978) — $50,000 paid 6/5/26, $75,978 outstanding; Pay App #3 ($144,836, Inv #1272) — fully billed. Total outstanding: $220,814 · 6-month promissory note 0% interest through 12/31/2026 · $90K due 7/1/2026 from Tivoli TI draw.
Jones Sign CoSignage Fabrication & Install$12,2753.1% Invoice 313293 ($7,904.61) paid in full Apr 30 via ACH. $966 credit agreed (after-hours + permit adjustment) — refund pending. Net cost $12,275. Install May 14 evening.
Precision TintWindow Film / Tint Installation$3,5620.9% Window tint installed 6/2/2026 (Sarah Tannis coordinated). Quote forwarded by Ike 6/1. PAID IN FULL via QuickBooks ✓
$390,767
Payment & Billing Tracker
DocumentDateFromAmountNotes
Pay App #1 (Invoice 1230)3/13/2026LV Builders$104,116.5030% completion — Base contract only
↳ Check #1374/1/2026→ LV Builders$62,000.00First payment
↳ Check #1394/20/2026→ LV Builders$42,116.50Final payment — FULLY PAID ✓
Pay App #2 (Invoice 1239)4/15/2026LV Builders$125,978.00Per QBO A/P. Due 5/15/2026. 38 days past due.
↳ Payment6/5/2026→ LV Builders$50,000.00Partial payment
↳ OutstandingLV Builders$75,978.00OVERDUE — included in promissory note
Pay App #3 (Invoice 1272)6/15/2026LV Builders$144,835.50Final billing — includes CO-1 $19,285 + CO-2 $8,590 at 100%. Full LV Builders contract now billed.
↳ Promissory Note6/24/2026LV Builders → Trillium House$220,813.506-month note for full outstanding balance (PA#2 $75,978 + PA#3 $144,836). $90K due 7/1/2026 (from Tivoli TI draw); remaining $130,814 in 6 monthly payments of $21,802.25 (7/31–12/31/2026). 0% interest if paid by 12/31/2026; 10%/yr after. Sign as The Trillium House. Section 10 needs attorney review.
Jones Sign (Bill 313293-D)1/25/2026Jones Sign Co$10,673.00Full contract — fabrication + install
↳ ACH Payment2/17/2026→ Jones Sign$5,336.5050% deposit paid
↳ Final Payment (ACH)4/30/2026→ Jones Sign$7,904.61PAID ✓ — $966 credit subsequently agreed (after-hours removed + permit adjusted). Refund of $966 owed back to Eichholtz.
↳ Refund PendingpendingJones Sign →($966.00)$966 refund owed: $500 after-hours removed + permit adjusted $1,274 → $808. ACH or check requested.
Precision Tint Invoice6/1/2026Precision Tint$3,562.00Window film/tint installation — quote "Eichholtz Las Vegas - Quotation (2).pdf" fwd by Ike 6/1
↳ QBO Payment6/2/2026→ Precision Tint$3,562.00PAID IN FULL ✓ via QuickBooks. Install completed 6/2/2026.
Total Billed to date:$391,733.11Pay App #1 $104,117 + Pay App #2 $125,978 + Pay App #3 $144,836 + Jones Sign $13,241 + Precision Tint $3,562
Total Paid to date:$170,919.61LV Builders $154,117 + Jones Sign $13,241 + Precision Tint $3,562
Outstanding A/P (LV Builders):$220,813.50Pay App #2 remainder $75,978 + Pay App #3 $144,836. Covered by promissory note through 12/31/2026. ($966 Jones Sign refund still pending.)
Scope Coverage Grid
INCLUDED
Metal Studs/Drywall
Base contract
INCLUDED
HVAC
Base contract
INCLUDED
Electrical
Base contract
INCLUDED
Plumbing
Base contract
INCLUDED
Unistrut
Base contract
INCLUDED
Demo + Concrete
Base contract
INCLUDED
Doors
Base contract
INCLUDED
Privacy Glass
Base contract
INCLUDED
Fire Alarm
Base contract
INCLUDED
Fire Sprinklers
Base contract
INCLUDED
Painting/LVP/FRP
Base contract
INCLUDED
Specialties
Base contract
CO-1
Cabinetry
$19,285
CO-2 (New)
Air Curtain (Main Entry)
$2,874
CO-2 (New)
Extra Circuits (Break Area)
$4,563
Jones Sign Co
Exterior Signage
$12,275 net (paid $13,241)
Precision Tint
Window Tint / Film
$3,562 (PAID ✓)